Tag: Enbridge

FLOW & Straits-Area Citizens Groups Call on State of Michigan to Deny Permits for ‘Line 5’ Oil Pipeline Tunnel in Straits of Mackinac

Citing inadequate legal authorization, an incomplete application, and lack of a comprehensive state review, FLOW and two Straits-area citizen groups called today in formal comments on the State of Michigan to deny pending permits sought by Enbridge to construct and operate a roughly four mile-long tunnel under the Great Lakes. 

The Canadian corporation’s giant tunnel, at roughly 20-feet in diameter, would house a new Line 5 pipeline to continue for another 99 years carrying up to 23 million gallons of oil and natural gas liquids a day through the public trust bottomlands of the Straits of Mackinac, where Lake Michigan connects to Lake Huron.

The comments by FLOW, the Straits of Mackinac Alliance (SMA), and the Straits Area Concerned Citizens for Peace, Justice, and the Environment (SACCPJE) came at today’s deadline in legal and technical comments directed to the Michigan Department of Environment, Great Lakes, and Energy (EGLE) and Michigan Department of Natural Resources (DNR). The groups’ comments identify critical deficiencies in the project’s construction permit application filed in April, its legal authorization, and the review by state environmental agencies of expected impacts to wetlands, bottomlands, and surface water, including from the daily discharge of millions of gallons of wastewater during construction.

“Enbridge’s attempted private takeover of the public’s bottomlands under the Straits of Mackinac for the tunnel project is not authorized by the state, not good for the climate or Gov. Whitmer’s goals, not good for public health, safety, and welfare, and not consistent with public need as the nation and world turn to clean energy for survival,” said Liz Kirkwood, executive director of FLOW, a Great Lakes law and policy center based in Traverse City. 

“We share the public’s deep concerns about the Canadian pipeline company’s tunnel proposal and its lack of necessity, and risks it would pose to the Great Lakes, drinking water, the fishery in the Straits, Tribal rights, the Pure Michigan economy, the climate, and a way of life,” said Kirkwood. “The biggest consequence right now of this proposed project is that it distracts the government from its duty to shut down the current Line 5 oil pipelines that pose a clear-and-present danger to the Great Lakes.”

To date, more than 2,600 members of the public—including individuals, families, business owners, community leaders, organizational leaders, and others—have filed comments with EGLE urging the agency to reject Enbridge’s proposed tunnel permits. Many groups, including FLOW and Oil & Water Don’t Mix, have articulated scientific and legal deep concerns about the Canadian pipeline company’s tunnel proposal and its lack of necessity, and risks to the Great Lakes, drinking water, the fishery in the Straits, Tribal rights, the Pure Michigan economy, the climate, and a way of life.

The comments Enbridge’s proposed oil pipeline tunnel submitted today by FLOW, SMA, and SACCPJE determined that EGLE:

  1. Cannot properly proceed on administering the Enbridge permit applications unless and until the December 2018 easement and tunnel lease have been authorized under the Public Trust Doctrine (PTD) and Great Lakes Submerged Lands Act (GLSLA);  
  2. Must undertake an analysis of the lifetime greenhouse gas emissions attributable to the proposed tunnel, particularly in light of Governor Whitmer’s Executive Directive 2020-10 setting a goal of economy-wide carbon neutrality by 2050. Extending the life of Line 5 for the next 99 years with  the tunnel project is fundamentally at odds with the reduction of greenhouse gases necessary to avoid the most catastrophic effects of climate change.
  3. Is required to measure the benefits of the proposed tunnel against its reasonably foreseeable detriments, under Part 303 of the Natural Resources and Environmental Protection Act (NREPA), which includes determining the:
    1. Public and private need for the project; and 
    2. Availability of feasible and prudent alternative locations and methods to accomplish the expected benefits from the activity; and
  4. Is required to comprehensively and independently consider and determine whether the tunnel project is consistent with protection of Michigan’s natural resources under the Michigan Environmental Protection Act (MEPA). The state must determine whether extending the life of an oil pipeline that will emit approximately tens of  million tons of greenhouse gases annually for the next 99 years, under the state NREPA, “is consistent with the promotion of the public health, safety and welfare in light of the state’s paramount concern for the protection of its natural resources from pollution, impairment or destruction.”

EGLE expects to issue its final decision on the oil pipeline tunnel permits and for wastewater impacts in late November and impacts to wetlands and submerged lands in early December. While Enbridge takes an estimated 5-10 years to study, seek permits, and build an oil tunnel, the 67-year-old Line 5 oil pipelines in the Straits would continue to decay and endanger the Great Lakes, jobs, and the drinking water supply for half of Michiganders. 

“The unique characteristics of the Straits of Mackinac make the area incredibly susceptible to disruption and destruction if EGLE approves the permits for Enbridge’s proposed tunnel,” said Patty Peek, Chair of the Straits of Mackinac Alliance. “The surrounding wetlands, shorebirds, waterfowl, and aquatic species will be in jeopardy from the millions of gallons of wastewater to be discharged daily into the surface waters of the Great Lakes. Local drinking water wells may be polluted and/or drilling operations may imperil the aquifer. Missing information and a lack of specificity on applications cannot be acceptable. The risk to our precious waters is too great to allow this tunnel project to move forward.”

For more information, see:

Comment by Oct. 19 on Permits for Risky Line 5 Oil Tunnel

enbridges-line-5-under-the-straits-of-mackinac

On Monday, October 19, the Michigan Department of Environment, Great Lakes, and Energy (EGLE) will conclude its public comment period on pending state permits for the expected wetland and wastewater impacts, and alternatives to constructing and operating Enbridge’s proposed, roughly four mile-long oil tunnel under the Great Lakes. The proposed tunnel, at roughly 20-feet in diameter, would house a new Line 5 pipeline to continue for another 99 years carrying up to 23 million gallons of oil and natural gas liquids a day through the public trust bottomlands of the Straits of Mackinac, where Lake Michigan meets Lake Huron.

It’s important for the members of the public—including individuals, families, business owners, community leaders, and others—to submit comments. Many people and groups, including FLOW and Oil & Water Don’t Mix, already have expressed deep concerns about the Canadian pipeline company’s tunnel proposal and its lack of necessity, and risks to the Great Lakes, drinking water, the fishery in the Straits, Tribal rights, the Pure Michigan economy, the climate, and a way of life. 

Below is guidance from FLOW on what to include in your written comments and how to submit them online by Monday’s deadline. EGLE expects to issue its final decision on the oil tunnel permits and for wastewater impacts in late November and impacts to wetlands and submerged lands in early December.

Points to Make in Public Comments by Oct. 19

FLOW is providing this content for you to draw from and supplement with your own information and perspective in your comment to EGLE on the proposed Line 5 tunnel permits:

  • Not authorized by the state — EGLE cannot properly proceed on administering the Enbridge permit applications unless and until the December 2018 Easement and tunnel lease have been authorized under sections 2 and 3 of the Great Lakes Submerged Lands Act and the Public Trust Doctrine.
  • Not good for the climate or Gov. Whitmer’s goals  — EGLE must take into account the lifetime greenhouse gas emissions attributable to the proposed petroleum tunnel, particularly in light of Governor Whitmer’s Executive Directive 2020-10 setting a goal of economy-wide carbon neutrality by 2050. Extending the life of Line 5 for the next 99 years with  the tunnel project is fundamentally at odds with the reduction of greenhouse gases necessary to avoid the most catastrophic effects of climate change.
  • Not good for public health, safety, and welfare — EGLE is required to determine whether extending the life of an oil pipeline that will emit approximately tens of  million tons of greenhouse gases annually for the next 99 years, under the state Natural Resources and Environmental Protection Act, “is consistent with the promotion of the public health, safety and welfare in light of the state’s paramount concern for the protection of its natural resources from pollution, impairment or destruction.”
  • Not a public need for the oil tunnel — EGLE must make a number of specific determinations, including whether the benefits of the project outweigh reasonably foreseeable detriments, the extent to which there is a public and private need for the project, and whether there are feasible and prudent alternatives to the tunnel project. Unless these determinations are clearly demonstrated by the applicant Enbridge, the permit is prohibited by the Michigan Environmental Protection Act and the Wetlands Protection Act.

How to Submit Your Comments to EGLE by Oct. 19

Be sure to submit your comments on Enbridge’s proposed Line 5 oil tunnel by the Monday, Oct. 19 deadline. The public can submit comments either by email to EGLE-Enbridge-Comments@Michigan.gov — referencing Application Number HNY-NHX4-FSR2Q — or via two EGLE web pages for commenting separately on each of the permits. Click on each link below and follow the instructions provided by the state:  

  • EGLE public comment page for Part 303 wetland impacts and Part 325 Great Lakes submerged lands impacts.
  • EGLE public comment page for National Pollutant Discharge Elimination System (NPDES) wastewater impacts.

How to Learn More about Line 5 and the Risky Oil Tunnel

To learn more about Enbridge Line 5 and the proposed oil tunnel, see these resources on FLOW’s website:

Thank you for speaking up for the Great Lakes, drinking water, and a way of life here in the Great Lakes State!

Speak Up for the Great Lakes at EGLE’s Line 5 Tunnel Hearings Starting Tuesday

enbridges-line-5-under-the-straits-of-mackinac-4f9997139d321d60

Starting Tuesday, Sept. 29, the Michigan Department of Environment, Great Lakes, and Energy (EGLE) will host four online public hearings and receive public comment on the expected wetland and wastewater impacts of constructing and operating Enbridge’s proposed, roughly four mile-long oil tunnel under the Great Lakes. The tunnel would house a new Line 5 pipeline to continue carrying up to 23 million gallons of oil and natural gas liquids a day through the public trust bottomlands of the Straits of Mackinac, where Lake Michigan meets Lake Huron.

It’s important for the members of the public—including individuals, families, business owners, community leaders, and others—to sign up ASAP to comment at these online public hearings using the links below because public comment during the meetings likely will be first-come, first-served.

To assist you, FLOW is providing guidance below on the public hearing schedule that runs from Sept. 29 to Oct. 8, how to sign up to comment, key points to consider making, and a template email you can tailor and submit as your written comment too by the Oct. 19 written comment deadline.

Hearing Schedule—Click a link below to register via Zoom and select “Yes” where it asks, “Would you like to make an official comment at this hearing?”:

Points to Make in Public Comments at the Public Hearings — FLOW is providing this content for you to draw from and supplement with your own information and perspective. EGLE will provide up to 3 minutes for each public comment. Start by stating your name, where you live, and if you are representing an organization, indicate which one. Here’s our guidance:

Not in Support:

  • I urge EGLE and the state of Michigan to deny Enbridge’s wetlands resource and NPDES wastewater permit requests to build a tunnel for the Line 5 oil pipeline through the public trust bottomlands of the Straits of Mackinac for the following reasons: 1. Enbridge’s application and project description is too narrow, and does not consider the cumulative effects, the existence of alternatives to the tunnel and wetlands related project purpose pursuant to Sections 303011(1) and 30311(4)(b) of the Wetland Protection Act.

Not Lawful:

  • Not authorized — The new easement (December 2018) granted by the former Snyder administration to the Mackinac Straits Corridor Authority and assigned to Enbridge for the proposed tunnel is invalid because it has not been authorized based on the required determinations of the Part 325 of the Great Lakes Submerged Lands Act and/or section 2129 of the public utility easement in bottomlands of Great Lakes law, MCL 324.2129.

Not a Solution, nor the Best Alternative:

  • It is clear that taking 5-10 more years to study, seek permits, and build a crude oil tunnel under the Straits of Mackinac is not a solution because it fails to address Line 5’s immediate threat to the Great Lakes and Pure Michigan economy and the risk posed by the pipeline’s more than 400 stream and river crossings in the Upper and Lower Peninsulas. 
  • Enbridge’s proposal to allow electrical lines and other infrastructure to occupy the proposed oil pipeline tunnel is a bad idea that poses an explosion risk.

Not Fully Disclosed:

  • Enbridge has indicated that the size of the proposed tunnel will increase from a 10 ft diameter to an 18-21 foot diameter, yet Enbridge continues to use the original estimate of $500 million. Since consumers will ultimately pay for the tunnel, it is important to determine the new estimated cost.  
  • The announcement by EGLE that it will defer to other agencies or the MPSC to consider the likely effects and alternatives of the proposed tunnel project is contrary to the law of Michigan under the Michigan Environmental Protection Act (MEPA). MCL 324.1701 and applicable court decisions.

Not Acceptable — Wastewater and Wetland Impacts:

  • Enbridge is requesting to release up to 5 million gallons/day of treated wastewater back into Lake Michigan on the south shore and up to 14 million gallons daily during storm events. What chemicals will be used in the tunneling process and how will the wastewater be treated to remove those chemicals? 
  • If the waters of the Straits are contaminated, there would be extremely negative impacts to fish populations, tribal fishing rights, and communities who rely on drinking water from the lake and tourism business. How can EGLE consider this permit without having the full details about treatment plans and what chemicals will be used?
  • Doubling the tunnel diameter also results in quadrupling the volume, with four times as much excavated materials to be removed, staged, and disposed of. What are the increased environmental risks associated with the excavation, staging and disposition of these materials?
  • Michigan courts have consistently recognized that the Michigan Environmental Protection Act (MEPA) imposes additional environmental review requirements that are supplemental to existing administrative and statutory requirements. Is EGLE conducting a thorough review under MEPA?

Not in the Public Interest:

  • A permit under Part 303 Wetland Protection “shall not be approved unless the department determines that the issuance of a permit is in the public interest… In determining whether the activity is in the public interest, the benefit which reasonably may be expected to accrue from the proposal shall be balanced against the reasonably foreseeable detriments of the activity.” Clearly this project is not in the public interest when considering the impacts to public surface waters, public bottomlands, public drinking water supplies, the climate, and economy.
  • A permit under Part 303 Wetland Protection Act “shall not be approved” unless the applicant demonstrates the “need” for the project; clearly, this project is not needed given the obvious decline in demand for oil in the U.S. and world, and because Enbridge’s and Michigan’s future needs for crude oil can be satisfied by the existing crude oil pipeline system in North American and the U.S; and, because the design capacity of Line 6b (now 78) across southern Michigan from Indiana to Sarnia and Detroit or Toledo was doubled when replaced in 2012-2014, which can reasonably handle all of the volume of crude oil and natural gas liquids transported by Line 5 and Straits dual pipelines.

Not Good for the Climate nor Economy:

  • Line 5 conveys approximately 8.4 billion gallons of oil and natural gas liquids per year, and when burned, yield over 57 million metric tons of CO2 annually. How can EGLE authorize the tunnel in the face of the incontrovertible evidence of environmental and economic harm caused by climate change? 
  • Oil when burned, releases carbon dioxide, carbon monoxide, nitrogen oxides, particulate matter, and unburned hydrocarbons, impairing air quality and having monetizable environmental and health impacts. EGLE must compare the social costs against the benefits.
  • Continued capital investment in fossil fuel infrastructure is fundamentally at odds with addressing the existential threat of climate change.
  • Federal agencies must determine the carbon emissions attributable to projects under the National Environmental Policy Act (NEPA); EGLE and the MPSC must undertake the same analyses under MEPA.
  • The construction of Enbridge’s proposed tunnel and pipeline project for the next 99 years is contrary to Governor Whitmer’s Executive Order on Building a Carbon Neutral Economy.  

Not the Best Alternative:

  • Under Part 303, EGLE must consider “the availability of feasible and prudent alternative locations and methods to accomplish the expected benefits from the activity.” EGLE must evaluate the following:
    • To what extent did the 2010 catastrophic failure and oil spill from Enbridge Line 6B into the Kalamazoo River watershed and the more recent temporary, full and then partial closure of Line 5 result in constriction of supply, market disruption, or price increases to end users?
    • Does Enbridge Line 6B in southern Michigan, now reconstructed with a larger diameter as Line 78, have the capacity to meet market demand if the tunnel is not built and Line 5 closes?
    • Is the carrying capacity of the existing network of North American pipelines sufficient to meet future needs? According to FLOW’s experts, available capacity and flexibility to meet energy demand in the Great Lakes region already exists in the North American energy pipeline system operated by Enbridge and its competitors without threatening our public waters and Pure Michigan economy.
    • Would cessation of Line 5 result in a new pipeline system equilibrium capable of meeting existing and future demand for oil and natural gas liquids?
    • What is the potential for the tunnel project to become a stranded asset and liability to the State of Michigan in the event market trends play out as predicted?

Written Comment Also Accepted — The public also can comment in writing at any time until EGLE’s comment deadline on Oct. 19. Here’s the:

  • Oil & Water Don’t Mix campaign’s public comment form for you to personalize — drawing from FLOW’s guidance provided above — and send, or you can use the EGLE links below.
  • EGLE public comment page for Part 303 wetland impacts and Part 325 Great Lakes submerged lands impacts.
  • EGLE public comment page for NPDES wastewater impacts.

Background — To learn more about Enbridge Line 5 and the proposed oil tunnel, see these resources on FLOW’s website:

Tribes and Environmental Groups Will Help Decide Fate of Proposed Line 5 Oil Tunnel in the Great Lakes

enbridges-line-5-under-the-straits-of-mackinac-4f9997139d321d60

MPSC seeks public comments online and at August 24 public hearing

Jim Olson is FLOW’s Founder, President, and Legal Advisor

By Jim Olson

Good news arrived recently for citizens concerned about Enbridge’s dangerous Line 5 pipelines that convey millions of gallons of petroleum each day, and the proposed massive new tunnel pipeline in the Straits of Mackinac — the very heart of the Great Lakes.

Administrative Law Judge Dennis W. Mack, who is handling the contested case for the Michigan Public Service Commission (MPSC) on Enbridge’s application for the Line 5 tunnel and tunnel pipeline, issued a ruling August 13 granting intervention to participate in the case to several federally recognized Indian tribes in Michigan and key environmental groups, including FLOW, that petitioned to bring special knowledge and expertise to the case.

The Administrative Law Judge (ALJ) granted intervention to a total of 13 entities, including four tribes — Bay Mills Indian Community, Grand Traverse Band of Ottawa and Chippewa Indians, Little Traverse Bay Bands of Odawa Indians, and the Nottawaseppi Huron Band of the Potawatomi, providing the first three tribes listed with an opportunity to formally assert their treaty rights this way for the first time. The Nottawaseppi Huron Band, based in Calhoun County, will bring their knowledge and experience gained by living near the site of Enbridge’s disastrous Line 6B pipeline spill in 2010 into the Kalamazoo River watershed. 

The ALJ also granted intervention to five environmental organizations — the Environmental Law & Policy Center with the Michigan Climate Action Network, For Love of Water (FLOW), Michigan Environmental Council, National Wildlife Federation, and the Tip of the Mitt Watershed Council — with reach across the state of Michigan, Great Lakes region, and nation. The Mackinac Straits Corridor Authority, Michigan Attorney General, Michigan Laborers’ District Council, and Michigan Propane Gas Association & National Propane Gas Association also were allowed to intervene in the case.

Enbridge filed a 17-page objection to the intervention by the organizations’ and tribes’ participation as parties in the case, taking the extreme position that since the MPSC granted approval in 1953 for the existing Line 5 in the Straits of Mackinac, Enbridge doesn’t need approval now for the proposed half-billion-dollar tunnel and tunnel pipeline.

FLOW and other organizations filed replies to Enbridge’s objection to their intervening in the case, pointing out that the MPSC in June had already rejected the company’s attempt to cut off further review and obtain immediate approval of the project without a comprehensive review of necessity, public interest at stake, impacts, and alternatives to the massive project. Over Enbridge’s objections, Judge Mack recognized the significant interests and rights and the unique perspective and expertise these organizations and sovereign tribes will bring to the case.

The comprehensive review and proceeding before the MPSC will continue in stages addressed by a scheduling memorandum entered August 13 by Administrative Law Judge Mack. Legal questions involving the nature and scope of the review required by the MPSC governing laws and regulations, the Michigan Environmental Protection Act (MEPA), and public trust principles that govern the Straits of Mackinac will be argued and decided between now and late October. After that, the case will proceed with discovery and exchange of information, direct testimony, rebuttal testimony, and cross examination of the testimony and evidence from late November until next summer, with a decision by the MPSC expected in early fall of 2021.

___________________________________________________________________________________________________________

Comment Now or at MPSC’s Aug. 24 Virtual Public Hearing

The Michigan Public Service Commission has invited public comments on Enbridge’s tunnel proposal through written submissions, as well as by telephone during an online public hearing scheduled for August 24, 2020. Oil & Water Don’t Mix, which FLOW co-leads with allied tribal and environmental groups, has created this easy tool for you to submit your comment to the MPSC opposing an Enbridge oil tunnel through the public bottomlands in the Straits of Mackinac. You also can sign up here or here to comment at the MPSC public hearing.

___________________________________________________________________________________________________________

See FLOW’s recent coverage of the Michigan Public Service Commission review of the Enbridge oil pipeline tunnel here:

Turning the Spotlight on Line 5 in the Great Lakes

enbridges-line-5-under-the-straits-of-mackinac-4f9997139d321d60

Jim Olson is FLOW’s Founder, President, and Legal Advisor

By Jim Olson

FLOW Founder and Legal Advisor

Last week the Michigan Attorney General’s Office chose not to appeal a lower court ruling upholding the constitutionality of a law that facilitates the framework for an oil tunnel under the Straits of Mackinac—forgoing any further challenge, but, in reality, yielding no strategic legal ground.

Don’t get me wrong. The constitutionality of the Act 359 “tunnel law” under the so-called “Title-Object” clause of article 4, section 24 of Michigan’s Constitution always has been an important question. This clause requires the purpose of a bill be stated in its title. Clearly, the legislature had no business stating the tunnel project was a public project like the Mackinac Bridge, then passing a law that allows a company to build, operate, and control its own private tunnel pipeline. 

But the tunnel law only sets up a framework for a tunnel and new pipeline in the Straits. By forgoing any further appeal of the “Title-Object” question, the spotlight turns on the more central question at hand:  

Can Canada’s Enbridge obtain the required authorizations under the rule of law, for its private gain and control, for a massive tunnel and tunnel pipeline beneath the public trust bottomlands of the Great Lakes?

The lame-duck legislature’s tunnel law and agreements signed by the Snyder Administration in its last days in 2018 sought to tie the hands of the newly elected Governor Gretchen Whitmer and Attorney General Dana Nessel, who took their oaths of office on January 1, 2019. But the 11th-hour maneuvers failed to bind the new leaders. Why? Because Act 359—the tunnel law—and the related tunnel agreements compel Enbridge to obtain the required approvals and permits for the location and construction of the tunnel and tunnel pipeline under all applicable federal and state laws. In other words, constitutional or not, the law simply begs the question.

The tunnel is not a done deal. Under the law, Enbridge is required to obtain a long list of governmental approvals and permits. Notably, it needs authorization under Michigan’s Great Lakes Submerged Lands Act (GLSLA) for easements and leases for location of the tunnel, a construction permit, and authorization to locate the pipeline in the tunnel as a “public utility” under the public trust bottomlands of the Great Lakes. 

Moreover, Enbridge can’t even apply for location of the tunnel pipeline until it obtains certification of the new line as a “public utility” from the Michigan Public Service Commission (MPSC). Thus, in addition to the required authorizations under the GLSLA, Enbridge also must prove and the MPSC must make findings that the tunnel is “necessary” and “in the public trust interest” in the uncertain and tumultuous world of 2020—declining crude oil markets, climate change, and rapid transition to a renewable economy that just may make life livable for our children and grandchildren in this century.

Not only are these findings required, but the MPSC also must find that there are no “likely environmental impacts” and that there are “no feasible and prudent alternatives” to the new tunnel—when there are thousands of miles of crude oil pipelines owned by Enbridge and its competitors crisscrossing North America in every direction. Enbridge’s  super-sized replacement of the ruptured Line 6B pipeline that despoiled the Kalamazoo River in 2010 has enough unused design capacity to nearly equal the average amount of crude oil pumped through Line 5 every day. The proposed oil tunnel is not necessary, clearly not in the public interest at this time in history, and there are alternatives that are both feasible and prudent.

After the tunnel law passed, Enbridge received an assignment of an easement and a 99-year lease-back from the Michigan Department Natural Resources (DNR) to locate, use, and operate the proposed tunnel and tunnel pipeline under the bottomlands of the Great Lakes. But Governor Snyder, the DNR, and Enbridge have not applied for authorization of this conveyance and lease under public trust law and the GLSLA. And, the tunnel and tunnel pipeline have not been certified by the MPSC. Nor has the project been authorized by the United States Army Corps of Engineers.

So, it is not surprising the constitutionality of the tunnel law aside, the central effort at this point must seek a prompt shutdown of the imminently dangerous conditions surrounding the existing dual pipelines in the Straits of Mackinac. And, as for the tunnel, the spotlight must determine whether the massive tunnel project should or can ever be approved under the rule of law of Michigan—the laws that protect the constitutional and public trust interests of our quality of life.

It’s time to navigate what we face in the 21st century, rather than remain stuck in the irons of the 20th century, when the 67-year-old Line 5 was installed in the open waters of the Great Lakes.

 

Line 5 Must Be Closed Before Disaster Strikes

The 67-year-old  dual Line 5 pipelines continue to operate in the Straits of Mackinac, threatening the Great Lakes with a massive oil spill from a leak or rupture in the worst possible place in the country. Hazards include strong currents, underestimated for the “as built” pipes, anchor strikes, and, now, we learn, anchor lines that dragged along the pipes, and tore out a saddle support, installed because the strong currents were scouring and undermining the original as built dual pipelines.

Attorney General Dana Nessel filed suit (Nessel v Enbridge) against Enbridge in Ingham County Circuit Court to decommission Line 5 in an orderly fashion to prevent well over $6 billion in damages and irreparable long-term harm should a spill occur. The existing Line 5 dual lines and this lawsuit must proceed. It is not, and should not be, tied to the proposed tunnel; these dual lines need to be closed down before an inevitable accident or rupture happens. Circuit Judge James Jamo has stopped use of the east leg of Line 5, and is considering the revocation of a 1953 easement that was given conditionally to Enbridge, but without any understanding of the conditions that exist in 2020.

An Enbridge Oil Spill on My Grandparents’ Farm

Photo: The clean up on the Zinn family farm in Marshall, Michigan, after Enbridge’s Line 6B failed a decade ago on July 25, 2010, eventually contaminating nearly 40 miles of the Kalamazoo River and its watershed with a million gallons of tar sands oil, sickening more than 300 people, permanently driving more than 150 people from their homes and properties, and destroying wildlife and habitat.

_________________________________________________________________________________________________

By Frank D. Zinn

Ten years ago, my uncle answered an early morning phone call. He lives in Ann Arbor, about 60 miles east of Marshall, the location of the Zinn family farm. The call was from a Marshall neighbor who reported that something was happening on the Zinn property — there was a gas or oil leak, and things looked and smelled really bad.

The Zinn farm in 2008 before the Enbridge Line 6B oil spill.

My aunt and cousin drove to the farm the next day to check things out. Things did indeed look and smell bad — there was a thick layer of oil sludge on the surface of Talmadge Creek, a tributary of the Kalamazoo River, which runs across the north end of the property. At that point it was clear that a pipeline had ruptured — but the extent of the spill and damage was not yet known.

Several days later, I joined my uncle and father to visit the property again. We met with a lawyer who represented Enbridge, the owner-operator of the Line 6B pipeline. We learned that the rupture occurred a few yards from our property line and that Enbridge was starting the process of cleaning it up and would therefore require access to our property. The lawyer told us that things were not as bad as they looked, and that Enbridge had everything under control. He said “a year from now, you won’t even know this happened” and reassured us that Enbridge would restore the land to be better than it was before the spill.

The 6-foot gash on Enbridge Line 6B that gushed more than 1 million gallons of heavy tar sands oil into the Kalamazoo River watershed when it failed on July 25, 2010.

The scene was a difficult one for my family. The farm had been in the family since about 1930 when my great-grandfather bought part of the property. My grandparents moved their young family there in 1947, so it was where my father and his siblings spent much of their childhoods. After my grandfather died in 1996, my aunt and uncle restored the 440-acre property to indigenous prairie to honor the legacy of his environmentally minded parents. During the two years before the spill, my family collaborated with a Chicago-based developer to design an eco-friendly project for the farm — one that combined a vineyard and winery with housing. We had planned to launch the project in the fall.

At the start of the clean-up process, my family gave Enbridge the benefit of the doubt and remained hopeful that we could proceed with our plans. However, after a few weeks it became clear that the extent of the damage was such that the eco-development project would no longer be feasible. We learned, for example, that Enbridge was immediately notified by its pressure sensors that there was a problem, but did not shut the line down for 17 hours, allowing approximately one million gallons of oil to escape (ignoring the company’s much-touted “policy” that a pipeline would be shut down within 10 minutes if the cause of an alarm could not be determined).

Cleanup of the Enbridge Line 6B oil spill on the Zinn farm, 2010

Moreover, the cleanup was not well designed or implemented, and, as a consequence, nine months into the process, Enbridge was ordered by the U.S. Environmental Protection Agency (EPA) to go back and do it again. Enbridge had failed to account for the fact that the heavy, tar sands crude oil broke down to be heavier than water, and therefore could not be simply skimmed off the surface of the water. At the end of the cleanup, the EPA and Enbridge admitted that at least 5% (about 50,000 gallons) would never be recovered.

After many months of getting little or no response from Enbridge to our questions about the extent of contamination and their plans to restore the property, my family felt it had no other option but to file a lawsuit. After a difficult and painful legal process, we finally settled with Enbridge. Enbridge bought the farm. The project we designed to honor my grandparents would not be built.

Cleanup of the Enbridge Line 6B oil spill on the Zinn farm, 2010

When Lakehead Pipeline Co. (Enbridge’s Line 6B predecessor) came to my grandfather in 1969 and offered to purchase an easement under the farm, he refused, citing his concerns about the environmental impact a spill would have. Lakehead took my grandfather to court in order to obtain the easement, and a Lakehead engineer testified under oath to a judge that a significant spill could never occur because three separate monitoring devices would immediately shut down the pumping station in the event of a rupture. Lakehead was awarded the easement on the basis of that testimony.

Enbridge acknowledges that its pipelines had 610 spills that released more than 5.5 million gallons of crude oil into the environment between 1999 and 2008. Enbridge’s inspections of Line 6B identified 140 instances of cracks/corrosion in 2007, and an additional 250 instances in 2009 — only 61 of these were repaired.

On July 15, 2010, just 10 days before Enbridge Line 6B ruptured, Enbridge’s vice president of U.S. operations for Enbridge Liquid Pipelines, Richard Adams, testified before the U.S. House of Representatives Subcommittee on Railroads, Pipelines, and Hazardous Materials. The focus of the hearing was on Enbridge’s Pipeline Integrity Management. In his testimony, Adams lauded the Enbridge Integrity Management Program and, under questioning, testified that the detection of large leaks in Enbridge pipelines were “almost instantaneous” by Enbridge control center personnel and that, if there was any uncertainty, they would shut down the pipeline.

So, the promises made to my family by the Enbridge lawyer a few days after the spill were not kept. The impacts of the spill on the farm are still evident, and the land is not better than it was before the spill. The statement made by the Lakehead engineer in 1969 was not true. Nor was the testimony made to the U.S. House of Representatives by an Enbridge vice president a few days before the spill.

Furthermore, it is clear that the pipeline regulation is not adequate. While the largest fine in history was levied against the company after a blistering accident report was issued by the National Transportation Safety Board (NTSB) in 2012, Enbridge looks to be back to business as usual (here’s a link to the NTSB report).  Many of the claims made by Enbridge about its Line 5 pipeline that runs through the Straits of Mackinac sound eerily similar to the claims it made about Line 6B before the spill a decade ago.

FLOW, Environmental, and Tribal Groups Urge U.S. Army Corps to Reject Enbridge Line 5 Tunnel Permit

enbridges-line-5-under-the-straits-of-mackinac-4f9997139d321d60

Enbridge’s request for federal approval of a Line 5 replacement oil pipeline in a proposed tunnel in the Straits of Mackinac should be rejected to protect the Great Lakes from the continued risk of a catastrophic oil spill and a pipeline that is no longer needed, 10 leading environmental and tribal groups said Tuesday in comments to the U.S. Army Corps of Engineers.

Citing a federal court order on July 6 involving the Dakota Access pipeline that also involves Enbridge, the groups told the Army Corps it cannot give rubber-stamp permit approval to Enbridge’s massive Great Lakes oil pipeline tunnel construction project without conducting an environmental impact statement (EIS) as required by the National Environmental Protection Act (NEPA).

“The biggest consequence right now of this proposed project is that it distracts the government from its duty to shut down a risky oil pipeline in the Great Lakes. Instead, we are talking about a proposed oil tunnel that may or may not ever be built,” said Liz Kirkwood, executive director of FLOW. “However, if Enbridge insists on this, then a full environmental review of this tunnel proposal is required. That’s what a federal court told the Army Corps, and that’s what we are telling the Army Corps. There’s no shortcut when it comes to potential risks to the Great Lakes.”

In their 22-page comment to the Army Corps, FLOW, Sierra Club, Clean Water Action, Northern Michigan Environmental Action Council, Straits of Mackinac Alliance, Groundwork Center for Resilient Communities, TC350.org, Straits Area of Concerned Citizens for Peace Justice and the Environment, Chippewa Ottawa Resource Authority (“CORA”), and Michigan League of Conservation Voters (“MLCV”) requested a public hearing on the proposed permit and a thorough review of the tunnel project under the National Environmental Policy Act. So far the Army Corps has failed to set a public hearing or undertake an environmental assessment of the proposal. A federal judge in July ordered the shutdown of the Dakota Access pipeline in Missouri after ruling in March that the Army Corps failed to conduct a full environmental review of the proposed pipeline project.  Enbridge also has an ownership stake in the Dakota Access pipeline

In separate comments filed with the Army Corps, five Michigan tribes with treaty rights to the Straits, said the massive proposed tunnel project is a threat to the spawning and fishing grounds for 60 percent of the commercial tribal whitefish catch.

“Whether it is a 67-year-old pipeline aging under pristine freshwater, or a proposed tunnel creating pollution and causing disruption to tribal fishing industries for years, Enbridge should not be allowed to cut corners and bypass a full environmental review, something that Line 5 has never had,” said Bryan Newland, president of the Bay Mills Indian Community. “We’ve seen the exemptions made and lack of thorough pipeline equipment reviews result in surprises of corrosion, dents and the most recent screw anchor damage. With the company’s lack of transparency and poor track record, moving forward with a tunnel is putting pipelines and profits above the safety of Michiganders and the environment, allowing a potential oil spill to continue threatening our Great Lakes.”

In their comments, the environmental groups cited numerous concerns with Enbridge’s tunnel proposal and said oil and propane supplies that are needed can be delivered by other means. Major concerns with the proposal include impacts on drinking water quality from millions of gallons of wastewater discharge and a potential oil spill, significant impacts on the local tourism economy, rental housing, public safety and health systems from a multi-year construction project.  Additional risks include pipeline safety and financial exposure to the state from a tunnel abandonment by Enbridge or collapse, including the potential for an explosion involving hazardous liquids. Tunnel safety was cited in a 2019 letter by the American Transmission Company withdrawing any potential participation in the proposed tunnel project.

“This project tunnel project is a massive undertaking with huge water quality, coastal wetlands, drinking water contamination, and other impacts for the Great Lakes and Michigan,” said Anne Woiwode, Chair of the Sierra Club Michigan Chapter. “This involves a waterbody of international importance that is protected under the Clean Water Act and we expect the Army Corps to follow the law.”

Two Virtual Hearings, Two Real Steps Closer to Shutting Down Line 5 in the Great Lakes

enbridges-line-5-under-the-straits-of-mackinac

Take Action: Click Here to Urge Michigan’s Leaders to Shut Down the “Significantly Damaged” Line 5 Right Now

Jim Olson is FLOW’s Founder and Legal Advisor

 

 

By Jim Olson 

For the past 6 years, Canada’s Enbridge has maneuvered the State of Michigan into rounds of back-and-forth letters, meetings, and agreements that have done nothing but delay any enforcement action to shut down Line 5 in the Straits of Mackinac, where Lake Michigan meets Lake Huron. After two pivotal hearings on Tuesday, June 30, however, Enbridge has begun to lose its grip on the fate of its dangerous twin Line 5 crude oil pipelines in the public waters of the Straits. Two hearings, and the State and its citizens are two steps closer to shutting down the unstable twin crude oil pipelines once and for all without replacement.

1st Hearing: The Michigan Public Service Commission on Enbridge’s Proposed Oil Pipeline Tunnel

On the morning of June 30, in a virtual public hearing with hundreds of participants, the Michigan Public Service Commission (MPSC) approved 3-to-0 an Order that rejected Enbridge’s bid to avoid its obligation to prove it is entitled to locate and construct its proposed tunnel pipeline “in the public interest” and that it is necessary at this time in history. (See FLOW E.D. Liz Kirkwood’s reaction here).

The company argued that it didn’t need the MPSC’s approval of the pipeline tunnel because the State’s utility commission approved the necessity of the existing line in 1953. In an Order more than 70 pages long, the MPSC described the complexity and importance of the public interest and necessity for a crude oil pipeline in the Great Lakes in 2020, not 67 years ago. The Order included an outline of the depth of the issues posed by the tunnel proposal before the public panel, relying on extensive comments submitted by the Michigan Environmental Council and National Wildlife Federation, Michigan tribal governments, For Love of water (FLOW), Michigan’s Attorney General Dana Nessel, and many other organizations and citizens.

The submitted comments pointed to the overarching public interest and public trust in the Great Lakes, demand for crude oil, alternative routes, threats to the environment, and risks to the Great Lakes from climate change, such as high-water levels and damaged infrastructure. The Order requires Enbridge to prove under the scrutiny of the MPSC in a formal, trial-like proceeding that the pipeline tunnel proposal is in the public interest, necessary, and that there are no reasonable alternatives to shipping oil through its and North America’s massive pipeline system.

2nd Hearing: Ingham County Circuit Court on a Preliminary Injunction to Shut Down Existing Line 5 in Attorney General Dana Nessel for the People of Michigan versus Enbridge Energy

On the afternoon of June 30, after a 5-hour virtual hearing in Ingham County Circuit Court in Lansing, Circuit Court Judge James Jamo continued the temporary restraining order (“TRO”) he issued on June 22, shutting down the flow of oil through Line 5 in the Straits of Mackinac. Enbridge argued that historical in-line inspections and video footage of scrapes to the exterior of the pipes and a twisted support structure designed to minimize damage from strong currents demonstrated the steel pipelines themselves were safe. Enbridge introduced a letter from the federal Pipeline and Hazardous Materials Safety Administration (PHMSA) that stated the agency did “not object” to restarting the pipelines “based on the assurances of Enbridge.” Lawyers for Enbridge told the Court that if PHMSA says it’s safe, then the State and Court have no jurisdiction or power to interfere with restarting the lines, and that Enbridge should be able to reopen the lines. 

The Attorney General’s lead attorney told the Court that Enbridge hadn’t turned over all of the information related to Enbridge’s “assurances” to PHMSA and that the cause of the damage to the structure and lines remained unknown. He argued that without more information and independent review of what happened, there was no way Enbridge or the State could comply with the stringent due care and prudence obligations under public trust law to insure that the pipelines are not a danger to the waters, bottomlands, and people of Michigan. The public trust in the waters and bottomlands of the Great Lakes is derived from the State’s title granted to it when it joined the United States in 1837, and it can’t be impaired, endangered, or controlled by primarily private interests.

Judge Jamo probed Enbridge’s lawyers on whether PHMSA’s “non-objection” could deprive the State of its public trust jurisdiction by a letter based on only the assurances of Enbridge. The lawyers couldn’t give a clear answer, and by the end of the hearing it was clear that what PHMSA said was evidence of safety, was not conclusive of the broader duty of the State and the Court to determine whether there was a violation of the due care requirement to protect the public trust in the Straits.

At the end of the hearing, the Court continued the TRO issued June 22. On Wednesday morning, July 1, the Court issued an amended TRO, keeping the suspension of use of the lines in force, but allowing Enbridge to inspect the west leg of the dual lines in the Straits to see if it could be used in the near future “subject to any future order of the Court.”

Clearly, Judge Jamo has taken control of the risks associated with the location of crude oil pipelines in the Straits. The condition of the two lines has totally changed from 1953. Approximately 150 saddle supports (with 50 some more on the way) have been added since 2001 to stabilize the failure of the original lines because of powerful currents in the Straits. Two recent events damaged the coating on the west line and broke an anchor support on the east line. Enbridge inspectors were not sure what caused the damage, but they thought it appeared to be anchor strikes or other objects dragged by passing ships. This is alarming because this brings the total number of known strikes to dual lines to three in the last 18 months. It appears Judge Jamo is exercising due care in continuing the shutdown of the lines. He took the request for preliminary injunction under advisement. In the near future, he is expected to decide on a previous motion to rule that the 1953 easement allowing Enbridge to place the two lines in the Straits in the first place is no longer valid under the public trust laws that protect the Straits and all of the Great Lakes.

Ultimately, this case and the fate of Line 5 will turn on the reality that in 2020 the conditions and circumstances are not the same as 1953. The Line 5 twin pipelines in the water and across the lakebed are in the wrong place because of certain serious conditions that will continue to exist and cannot be controlled. Under public trust law, these lines and the easement that allowed them are no longer lawful. Attorney General Nessel did the right thing in filing this lawsuit—the lines in this location violate the public trust and constitute a public nuisance in the form of an “environmental ticking time bomb,” as the State has argued, that could go off at any time. How strong a current, how many near-disaster anchor-strikes or other errors will it take before the inevitable catastrophe happens? Now is the time to prosecute these claims to the right conclusion, a permanent and orderly shutdown.

In the meantime, Circuit Court Judge Jamo was correct in keeping this matter under his control and advisement, and to continue the temporary order suspending the use of these pipelines pending further proceedings. For the moment, the pumps and twin lines remain silent.

MPSC: Proposed ‘Line 5’ Oil Tunnel in the Straits of Mackinac Must Undergo Full and Vigorous Public Review

MPSC Chairman Sally A. Talberg

Photo above: MPSC Chairman Sally A. Talberg, presiding over the Commission hearing today on Enbridge’s proposed oil pipeline tunnel in the Straits of Mackinac.


FLOW E.D. Liz Kirkwood

The following statement can be attributed to Liz Kirkwood, environmental attorney and executive director of FLOW (For Love of Water), a Great Lakes law and policy center based in Traverse City:

“The Michigan Public Service Commission’s decision today is a big win for all Michigan residents that upholds their public trust rights in the Great Lakes. The MPSC flatly rejected the untenable claim by Enbridge that it had somehow already received approval in 1953, when Line 5 was built in the Straits of Mackinac, for an oil tunnel it is proposing 67 years later in 2020. The 3-0 vote by the MPSC means Enbridge will not be allowed to dodge a full review of their proposed oil pipeline tunnel, including an August 24 public hearing, which is desperately needed in light of the potential impact on the Great Lakes and its regional economy.

“We applaud the MPSC for rejecting Enbridge’s declaratory ruling request, and instead, requiring that Enbridge’s application be reviewed as a contested case with a public hearing under Michigan’s Act 16. Enbridge now has the burden to show a public need for this proposed oil pipeline under the Great Lakes, ensure no harm or pollution to our public trust waters and lands, and fully consider feasible and prudent alternatives to this project. With society’s urgent need to tackle climate change head on and ensure freshwater security, Enbridge cannot show that its proposed fossil fuel infrastructure is a credible solution for Michigan’s 21st century just and equitable future.”


See FLOW’s additional coverage of the MPSC review of the Enbridge oil pipeline tunnel here:

State Points to Fatal Flaw in ‘Line 5’ Tunnel Law

In Enbridge v. Michigan, the Court of Appeals Hears Arguments on Constitutionality of Lame-Duck Legislation Fast-tracked under Former Gov. Snyder

Photo: Robert Reichel, framed in green rectangle, an Assistant Attorney General at the Michigan Department of Attorney General, addresses the Michigan Court of Appeals on June 3, 2020, via Zoom, in the case, Enbridge v. State of Michigan.

Jim Olson is FLOW’s Founder, President, and Legal Advisor

By Jim Olson

What may seem like dry legal arguments over the interpretation of a few words sometimes can have ripple effects on people, health, safety, and the environment.

Such is the case with arguments heard June 3 before the Michigan Court of Appeals over the fate of the proposed Enbridge oil pipeline tunnel under the Straits of Mackinac, which promises to leave a lasting mark on the future of the Straits and the people of the Upper Great Lakes. (Click here to watch a video-recording of the Court of Appeals hearing).

In December 2018, the Legislature passed Act 359 as the Snyder Administration prepared to leave office. The goal of the Act was to help Canada’s Enbridge build, lease-back, use, and operate tax-free a tunnel to house a new pipeline to replace its decaying Line 5 crude oil pipeline snaking across the bottom of the Straits of Mackinac. In March 2019, Attorney General Dana Nessel, in a carefully written opinion, ruled that the tunnel law was unconstitutional because it violated article 4, section 24 of the Michigan Constitution.

As a result, state agencies could not process matters based on the proposed tunnel law because the Attorney General’s opinion was binding on those agencies.  A few months later, Enbridge filed a lawsuit against the State to nullify the Attorney General’s opinion and rule Act 359 constitutional and its tunnel pipeline deal valid, prevailing in the Court of Claims in October. The State appealed to the Court of Appeals for the arguments heard Wednesday and a decision.

State: Title of Tunnel Law Says One Thing, Does Something Else

The State of Michigan focused its argument in front of the Appeals Court on article 4, section 24 of the Michigan’s Constitution, popularly labeled the “title-object” clause, which prohibits the legislature from saying a law’s purpose is one thing, when the text of the law is about something else or when adding other things that are not incidental to implementing the law’s purpose.

Let’s give this some context. For example, the legislature cannot state in legislation that it is acquiring state land to establish and operate a public state park, then convey the land to a private corporation to build and operate the park. Or, given the same example, the state law cannot expressly say the project is a public park, then provide in the law for also using the land for a race-track, which is not incidental to implementing a public park, the law’s purpose.

So, there’s good reason for this provision of the state constitution, because it prohibits the legislature from duping others, including the public, into thinking the law is about one thing, when in fact it is about another or multiple things. In short, as our Supreme Court has said, the purpose of the “title-object” limitation is to provide “fair notice” to legislators and the public and to prevent “subterfuge” or deceit on affected persons and the public.

Enter the COVID-19 “Zoom” Courtroom of the Michigan Court of Appeals

On June 3, Judges Cameron, Boonstra, and Letica heard arguments from Robert Reichel, a senior, career lawyer for Michigan’s Attorney General Dana Nessel, and John Bursch, a lawyer for Enbridge, over the constitutionality of Act 359 under the “title-object” clause of the Michigan Constitution.  There were no fireworks. Bob Reichel meticulously laid out the State’s two-fold arguments: 

  1. The title clause of Act 359 authorized the Mackinac Bridge Authority (“MBA”) to acquire and operate, or a new Mackinac Straits Corridor Authority (“MSCA”) to acquire and operate a state corridor utility tunnel for Enbridge’s oil pipeline and supposedly other utility electrical or natural gas lines under the Straits of Mackinac. But the provisions of the law itself authorized Enbridge, a private corporation, to acquire the bottomlands of the Straits, construct, transfer to the MSCA the title, but leaseback to Enbridge to control, occupy, and use the public trust bottomlands for 99 years, with little oversight.
  2. The title clause of Act 359 has a single object, the acquisition and operation of a public bridge by the authority for public vehicles. The body of the law has multiple purposes or objects, including transferring authority for the tunnel and pipeline to MSCA, assigning easements, entering into the 99-year lease, requiring the MSCA to review and sign a tunnel agreement, third agreement, authorizing Enbridge to sublease and manage the tunnel space, and requiring the Attorney General of Michigan to pay Enbridge’s legal costs if the Attorney General on behalf of the people of Michigan objects to the lawfulness of the tunnel and pipeline [Emphasis added].

Enbridge Downplays the “Who” and Expands the “What” in Tunnel Law

John Bursch for Enbridge avec bowtie, argued that the title clause of Act 359 covered infrastructure connecting the Upper Peninsula to the Lower Peninsula, so the tunnel and pipeline are surely part of the purpose and object. He also argued that it doesn’t matter “who” does the project, as long as it’s a government agency doing it, so the MSCA has full authority to sign agreements and to satisfy the project described in Act 359. As to multiple purposes not squarely within the title, he argued they were germane to carrying out the project.

Robert Reichel exercised his right to rebuttal and pointed out that both the “who” and “what” mattered.  In the “title” clause of Act 359, both the new Mackinac Straits Corridor Authority and older Mackinac Bridge Authority are authorized to acquire, establish, and operate a public project. But unlike the “title” clause, the body or provisions of Act 359 itself actually authorize Enbridge, a private entity, to control and operate the tunnel. After listening to arguments, none of the three judges asked any questions.

A Private Tunnel Project Paraded as a Publicly Operated One Is Subterranean Subterfuge

The way I see it, the scales of justice in this case tip precipitously in favor of the people of the State of Michigan and the integrity of the state constitution. The law should mean what it says, not what a lame-duck legislature concocts in the last weeks of 2018 to satisfy the desires embodied in self-serving agreements between Enbridge and the Governor’s executive office. Ironically, these agreements themselves offer up the violation of the title-object clause.  

The 1952 law creating the Mackinac Bridge Authority provided for the establishment and operation of a public project, financed by the public, and managed and operated by the public through the MBA and Michigan Department of Transportation. The title clause of the 2018 tunnel law, Act 359, represents the same thing, a public utility tunnel, owned and operated by the MSCA, a state governmental body.  In fact, the body of the law provides for a complex set of agreements, rights, and duties that hands the tunnel and pipeline control, and control of other utilities, and operation entirely to Enbridge with relatively little paper-shuffling control by the MSCA. Paragraph G of the Second Agreement, signed by Snyder and Enbridge in October 2018, contains this glaring admission: 

The State and Enbridge agree to initiate discussions, as soon as practicable, to negotiate a public-private partnership agreement with the Mackinac Bridge Authority (“Authority”) with respect to the Straits Tunnel for the purpose of locating the Line 5 Straits Replacement Segment and, to the extent practicable, Utilities in that Tunnel (hereinafter “Tunnel Project Agreement”)… [T]he Authority would execute a lease or other agreements to: (a) authorize Enbridge’s use of the Straits Tunnel for the purpose of locating the Line 5 Straits Replacement Segment for as long as the Line 5 Straits Replacement Segment shall be in operation by Enbridge; (b) provide that Enbridge will operate and maintain the Straits Tunnel during the term of the lease on terms to be agreed; and (c) specify the conditions under which Utilities may gain access to the Straits Tunnel.

Nowhere in the “title” clause of Act 359 calling on the MSCA to establish and operate a tunnel does the law state that Enbridge will build, control, use, and operate a tunnel for as long as the tunnel is in operation. In the words of the Michigan Supreme Court, this does not provide fair notice to the log-rolling that took place in the last days of 2018. Worse, it constitutes a subterfuge and deceit on the people of Michigan that our constitution and courts prohibit.  

Attorney General Nessel was right when she issued her opinion in 2019; Act 359 is unconstitutional. If Enbridge wants to build and operate a tunnel, let it choose to design and apply for the authorization and permits to build a tunnel for its private crude oil pipeline under the laws of Michigan that apply to and protect the waters and bottomlands of the Straits of Mackinac and the Great Lakes.