Good news arrived recently for citizens concerned about Enbridge’s dangerous Line 5 pipelines that convey millions of gallons of petroleum each day, and the proposed massive new tunnel pipeline in the Straits of Mackinac — the very heart of the Great Lakes.

Administrative Law Judge Dennis W. Mack, who is handling the contested case for the Michigan Public Service Commission (MPSC) on Enbridge’s application for the Line 5 tunnel and tunnel pipeline, issued a ruling August 13 granting intervention to participate in the case to several federally recognized Indian tribes in Michigan and key environmental groups, including FLOW, that petitioned to bring special knowledge and expertise to the case.

The Administrative Law Judge (ALJ) granted intervention to a total of 13 entities, including four tribes — Bay Mills Indian Community, Grand Traverse Band of Ottawa and Chippewa Indians, Little Traverse Bay Bands of Odawa Indians, and the Nottawaseppi Huron Band of the Potawatomi, providing the first three tribes listed with an opportunity to formally assert their treaty rights this way for the first time. The Nottawaseppi Huron Band, based in Calhoun County, will bring their knowledge and experience gained by living near the site of Enbridge’s disastrous Line 6B pipeline spill in 2010 into the Kalamazoo River watershed. 

The ALJ also granted intervention to five environmental organizations — the Environmental Law & Policy Center with the Michigan Climate Action Network, For Love of Water (FLOW), Michigan Environmental Council, National Wildlife Federation, and the Tip of the Mitt Watershed Council — with reach across the state of Michigan, Great Lakes region, and nation. The Mackinac Straits Corridor Authority, Michigan Attorney General, Michigan Laborers’ District Council, and Michigan Propane Gas Association & National Propane Gas Association also were allowed to intervene in the case.

Enbridge filed a 17-page objection to the intervention by the organizations’ and tribes’ participation as parties in the case, taking the extreme position that since the MPSC granted approval in 1953 for the existing Line 5 in the Straits of Mackinac, Enbridge doesn’t need approval now for the proposed half-billion-dollar tunnel and tunnel pipeline.

FLOW and other organizations filed replies to Enbridge’s objection to their intervening in the case, pointing out that the MPSC in June had already rejected the company’s attempt to cut off further review and obtain immediate approval of the project without a comprehensive review of necessity, public interest at stake, impacts, and alternatives to the massive project. Over Enbridge’s objections, Judge Mack recognized the significant interests and rights and the unique perspective and expertise these organizations and sovereign tribes will bring to the case.

The comprehensive review and proceeding before the MPSC will continue in stages addressed by a scheduling memorandum entered August 13 by Administrative Law Judge Mack. Legal questions involving the nature and scope of the review required by the MPSC governing laws and regulations, the Michigan Environmental Protection Act (MEPA), and public trust principles that govern the Straits of Mackinac will be argued and decided between now and late October. After that, the case will proceed with discovery and exchange of information, direct testimony, rebuttal testimony, and cross examination of the testimony and evidence from late November until next summer, with a decision by the MPSC expected in early fall of 2021.

___________________________________________________________________________________________________________

Comment Now or at MPSC’s Aug. 24 Virtual Public Hearing

The Michigan Public Service Commission has invited public comments on Enbridge’s tunnel proposal through written submissions, as well as by telephone during an online public hearing scheduled for August 24, 2020. Oil & Water Don’t Mix, which FLOW co-leads with allied tribal and environmental groups, has created this easy tool for you to submit your comment to the MPSC opposing an Enbridge oil tunnel through the public bottomlands in the Straits of Mackinac. You also can sign up here or here to comment at the MPSC public hearing.

___________________________________________________________________________________________________________

See FLOW’s recent coverage of the Michigan Public Service Commission review of the Enbridge oil pipeline tunnel here: